Add a Gantt Curtain
Create one or more Gantt curtains and customize them according to your team's needs. You can add a Gantt curtain from the the Manage Views panel or directly from the Gantt chart on the Activities page while reviewing a project schedule.
Note: Gantt curtains must be enabled before you can display any Gantt curtains that you've added to a view.
To add a Gantt curtain on the Manage Views panel:
- Navigate to the Activities page
- In the object selector, select ﱆ Project or Program, and then select a project or a program from the list.
- From the Main Menu, select Schedule, and then select Activities.
- Select Activities Grid Settings.
- In the Manage Views panel, select the Gantt tab.
- At the top of the panel, select the Curtains tab.
- Select Add to create a new curtain, and then customize it with the available options:
- Name: Add a name for the Gantt curtain.
- Description: Add a significant description for your project team. This description displays with the Name and Start and Finish dates when a user hovers over the curtain name.
- Start: Enter the starting point for the curtain to display.
- Finish: Enter a finishing point for the curtain to close.
The default length of the curtain relates to the selected timescale. For example, if the timescale is set to Week/Day, then the default length is 1 week.
- Color: Apply a color to the curtain. The default selection is mint green.
- Opacity: Select an opacity level for your curtain. The range is 0 to 100%, with 100% being the default value.
- Visibility: Select this option to show or hide the curtain in Gantt view. When you create a new curtain, this option is selected by default.
- Apply the view:
In the Manage Views panel:
- Select Save. When selected, you are saving all changes to the current view.
- Select Save As. When selected, you can create a new Personal, Project, or Workspace view with a new name in the Save View as window.
- Select Apply. When selected, you are returned to the grid. The grid displays any changes you have made; however, those changes are not saved. To save changes select Save or Save As in the View list.
- Select Reset.
- Select Close.
In the Settings panel:
- Select Save.
To add a Gantt curtain from the Gantt chart on the Activities page:
- Navigate to the Activities page
- In the object selector, select ﱆ Project or Program, and then select a project or a program from the list.
- From the Main Menu, select Schedule, and then select Activities.
- In the Layout menu, select Gantt.
- Right-click on the Gantt chart, select Curtains, and then select Add.
- In the Manage Curtain dialog, customize your curtain settings with the following options:
- Curtain Name: Add a name for the Gantt curtain.
- Select Display Curtain Name to display the curtain name with the curtain.
- Curtain Description: Add a significant description for your project team. This description displays with the Name and Start and Finish dates when a user hovers over the curtain name.
- Start: Enter the starting point for the curtain to display.
- Finish: Enter a finishing point for the curtain to close.
The default length of the curtain relates to the selected timescale. For example, if the timescale is set to Week/Day, then the default length is 1 week.
- Color: Apply a color to the curtain. The default selection is green.
- Opacity: Select an opacity level for your curtain. The range is 0 to 100%, with the default being 100%.
- Display Curtain Attachment: Select this option to show or hide the curtain in Gantt view. When you create a new curtain, this option is selected by default.
- Curtain Name: Add a name for the Gantt curtain.
- Select OK.