Project Copy Dependencies
When copying a project from an existing project or template, all project data is copied by default, but you can also choose the data you want to copy. Certain data has dependent data, meaning that when you select to copy it, other options are selected as well. This topic lists the data options you can select and their dependent data.
When copying a project, you can also select whether to include project actuals in the project copy by moving the data sets to the Selected list on the What's Included step of the Add Project Wizard. Data on this step is organized by main category titles that have subcategories of data. You can move a main category title to the Selected list to move all of its subcategories over. If you move all of the subcategories in a main category to the Selected list, then the main category title will also be moved to the Selected list.
The title of each table in this topic is a main category title. The Subcategory columns are the subcategories in the main category. The Included Data columns include the application data that is included in each subcategory. The Dependent Subcategories column includes the subcategories that are automatically moved to the Selected list when you select the subcategory in the Subcategory column on that row. The Dependent Subcategories can't be removed from the Selected list unless you first remove the subcategory it is dependent on. The Included Data will also be copied for a dependent subcategory and the category it is dependent on.
For example, if you move Activities to the Selected list, then Calendars (Project) and WBS will also be moved to the Selected list and can't be removed unless you first remove Activities. All data for the Activities subcategory in the Included Data column (activities, activity default settings, calendar assignments, code assignments, configured field assignments, file assignments, and notebook topics) will be copied, and so will the data for project-level Calendars (all project-level calendars) and WBS (WBS, code assignments, configured field assignments, and notebook topics).
Note There is certain data that will always be included in project copy and isn't dependent on your choices on the What's Included step. That data includes project files and their code assignments, project-level risk fields, project settings (located on the Settings page of the project Summary & Settings), codes, configured fields, and user and user groups associated with the source project and their permission sets (although you can update these options on the Permission Sets step of the Add Project wizard).
Project Actuals
When you copy data from an existing project, you can choose to include or exclude actuals for the selected items. If you include actuals, all project actuals data from Resources & Roles, Risks, Schedule, and Tasks is copied into the template or new project. This includes parent and dependent items within each category.
For example, if you select Schedule and include actuals, then Activity Relationships and Resource Assignments are not available for selection because they are included with all Schedule actuals data.
Schedule
Subcategory | Included Data | Dependent Subcategories | Exclusions for Actuals |
---|---|---|---|
Activities | Activities, activity default settings, calendar assignments, code assignments, configured fields assignments, file assignments, notebook topics | Calendars (Project), WBS | All Activities fields will be copied when copying actuals except Activity Steps, Work Package Scope, Percent complete, and Percent Type Complete. Only Scope Type will be copied. |
Activity Relationships | Activity relationships | Activities, Calendars (Project), WBS |
|
Resource Assignments | Resource assignments, calendar assignments, roles and resources assigned to activities, schedule settings, curves, configured field assignments | Activities, Calendars (Project), WBS | All Assignment fields will be copied except Timesheet fields. |
Note
- If both Activities and Tasks are selected, then any Task Activity associations will be copied.
- If both Activities and Risks are selected, then any Risk Activity associations will be copied.
- When actuals are included, and a user selects Risk, then the entire Schedule will also be copied. Schedule cannot be moved to the left because Risk is dependent upon it. However, Schedule is not dependent on Risk and can be included without it.
- Stored Period Performance and Prior Actuals fields will not be copied from Activities and Assignments.
Resources & Roles
Subcategory | Included Data | Dependent Subcategories |
---|---|---|
All Project Resources | Resources, resource and role associations, calendar assignments, code assignments | All Project Roles, Units of Measure, Calendars (Project) |
All Project Roles | Roles, work rates, calendar assignments, code assignments | Unit of Measure, Calendars (Project) |
Note Resource and role associations are copied when All Project Resources and All Project Roles are both copied.
Risks
Subcategory | Included Data | Dependent Subcategories |
---|---|---|
Risks | Risks (threats, opportunities, weather, risk factor), Monte Carlo Analysis settings, risk and activity associations, risk response actions, risk quantified impacts, contingencies, configured field assignments, code assignments, project-level risk fields generated as a result of running a risk analysis, file assignments | Activities, Matrix, Calendars (Project), WBS |
Matrix | Matrix assigned to the project, Monte Carlo Analysis Settings, matrix and threshold data if a matrix is assigned to the project | None |
Activity Uncertainty | Activity uncertainty, Monte Carlo Analysis Settings | Activities, Calendars (Project), WBS |
Note
- The Period Start and Period Finish year for weather risk data will be updated to match the new project's start date. For example, if your Period Start date for a weather risk is June 1st, 2015, and your new project's Start date is January 15th, 2020, then the Period Start date for the weather risk will be June 1st, 2020 when it is copied.
- When actuals are included, and a user selects Risk, then the entire Schedule will also be copied. Schedule cannot be moved to the left because Risk is dependent upon it. However, Schedule is not dependent on Risk and can be included without it.
Tasks
Subcategory | Included Data | Dependent Subcategories | Exclusions for Actuals |
---|---|---|---|
Tasks | Tasks, calendar assigned to the project, owning company (all tasks will be reassigned to the project owning company), configured fields assignments, code assignments, and crew size estimates | None | When actuals are included, the status of all tasks will be copied except for committed tasks. The status of committed tasks will be changed to pending. Constraints and commitments will not be copied when actuals are included. |
Task Hand-offs | Task hand-offs | Tasks |
|
Note If both Activities and Tasks are selected, then any Task Activity associations will be copied.
Settings
Subcategory | Included Data | Dependent Subcategories |
---|---|---|
Autonumbering | Autonumbering | None |
Structures
Subcategory | Included Data | Dependent Subcategories |
---|---|---|
Calendars (Project) | Project-level calendars | None |
Codes (Project) | Project-level codes and code values | None |
Units of Measure | Units of measure | None |
WBS | WBS, code assignments, configured field assignments, notebook topics | None |
Custom Logs
Subcategory | Included Data | Dependent Subcategories |
---|---|---|
The subcategories for custom logs will be any existing custom log types in the project being copied. If the project being copied contains no custom logs, then there will be no options for them in the Add Project wizard. | Custom log configuration settings, code assignments, configured field assignments | None |
Note Custom log items will not be included in copy.
Last Published Monday, September 15, 2025