The information on the Summary Cost Sheet can come from many projects. Use Recalculate to make sure the Summary Cost Sheet shows the most up-to-date cost information.
To recalculate costs on the Summary Cost Sheet:
- In the object selector, select
Program, select View Programs List, and then select a program name.
- From the
Main Menu, select
Cost and Funds, and then select Summary Cost Sheet.
- On the Summary Cost Sheet page, select Recalculate.