Void a Change

You can void a change that should no longer be documented as having any impact on your commitments.

To void a change:

  1. In the object selector, select Project, select View Projects List, and then select a project name.
  2. From the Main Menu, select Contracts and Commitments, and then select Changes.
  3. On the Changes page, select the change that you want to void.

    You can only void changes that are In Progress.

  4. Select the Actions menu, and then select Void.