Reset the Project CBS
You can reset the project CBS if your project cost code needs change if the following conditions are met:
- CBS codes are not assigned to scope items, scope assignments, funds, or risks.
- CBS codes are not inherited by another CBS.
To reset the project CBS:
- In the object selector, select
Project, select View Projects List, and then select a project name.
- From the
Main Menu, select
Cost and Funds, and then select Cost Sheet.
- On the Cost Sheet page, select the Actions
menu, and then select Reset CBS.